This "Ski-in"
lodge style home
has a three car
garage with the
main level above.
The "team room"
is located off the
garage - for ski
waxing.
Home designed by Eric A. Anderson
Visit Eric's Website.
The beginning of excavation, first establish water for fire protection, then
put in construction limit fencing and storm water run-off protection.
A very large boulder was
struck during excavation. A
hammer was brought in for
the excavator, allowing him
to break up the boulder for
off-hauling.
It's pour day! The foundation crew is hard
at work. Next ARXX Wallsystem will be
used to build the retaining walls.
The Arxx Wallsystem is being installed.
Concrete is poured into the
Arxx Wallsystem, vibrated,
troweled, and then left to
hydrate.

The bracing system is removed
after a couple days.
Home designed by Eric A. Anderson
Visit Eric's Website.